How to Amend a Purchase Requisition

Summary

This manual guide you to change the quantity or price on a requisition you already submitted in Oracle Fusion Self Service Procurement. The change goes back through approval before it takes effect. You can only amend a requisition that has no purchase order (PO) yet. Once a PO is created, the requester can't edit it.

Body

Part 1: Requester amends the requisition

Step 1: Open Purchase Requisitions (New)

Log in to Oracle as the Requester. On the Home page, click the Procurement tab, then click Purchase Requisitions (New).

You should see: the Self-Service Procurement page.

Step 2: Find the requisition

My Requisitions: Click My Requisitions at the bottom of the page

Pick requisition: Pick a requisition that has no purchase order yet. Its status shows Pending approval or approved, not Ordered. If the row shows a purchase order number, it can't be amended.

Step 3: Open the requisition

Click the requisition number:

Click the requisition number link (for example, R10000248). You should see: the requisition details.

Step 4: Click Edit and confirm

Click Edit: Select three-dot menu for the requisition you want to edit.

Click in the Edit option.

In the pop-up box, confirm that you want to edit.

You should see: the requisition opens for editing.

Step 5: Edit the line

Select the line for edit: Click in the three-dot menu and select the line you want to change and click its Edit (pencil) icon.

Change the Quantity or Price: Change the Quantity or Price as needed, the subtotal will be adjusted as per edited price, quantity. You should see: the line shows the new quantity or price.

Step 6: Submit the change

Click Submit.

Click submit for the approval. You should see: the change order is submitted for approval.

Part 2: Requester checks the requisition

Step 1: Find and view the requisition

a) Log in as the Requester and open Procurement à Purchase Requisitions (New), as in Step 1. (Ignore this step if you are already logged in)

b) Click My Requisitions at the bottom of the page.

c) Optionally, search by requisition number or other details to narrow the list.

d) Click the requisition to see its details.

e) You can see the requisition details.

Part 3: Requisition Status Guide

The status on your requisition shows where it is in the process, from creation to delivery and payment.

a) Requisition stage (before it becomes an order)

Status

What it means

What to do (Requester)

Draft (Incomplete)

Created and saved but never submitted. Nothing has been routed for approval. This is by far your biggest bucket, so it’s mostly abandoned or forgotten carts.

Submit it, or delete it if it’s no longer needed.

Pending Approval

Submitted and sitting in the approval work flow.

Wait, or check approval details.

Approved

Fully approved but not yet turned into a PO. It’s waiting for a buyer or the auto create process to pick it up.

No action needed.

Rejected

An approver denied it.

Edit and resubmit it, or cancel it.

Returned

Sent back to the requester without a final denial, usually for edits before resubmitting.

Read the reason, edit and resubmit it.

Withdrawn

The requester pulled it back out of approval.

Edit and resubmit it, or cancel it.

Canceled

Canceled at the requisition level. It’s dead.

Create a new requisition if the item is still needed.

b) Fulfillment stage (after it becomes an order):

Status

What it means

Ordered

A Purchase Order (PO) has been created and issued to the supplier. This is the open-order bucket.

Order Processing

The order is in the middle of being created or transmitted, or the supplier has acknowledged it and it’s being processed.

On Negotiation

The buyer has flagged the line for negotiation (price or terms) before the PO is finalized. Common with RFQ-style or contract-pending items.

Order on Hold

The PO is on hold, so it can’t be received or invoiced.

Order Canceled

The PO or PO line was canceled after being created.

On Contract

The requisition line is tied to a contract or agreement instead of a standard PO.

Shipped

The supplier has sent an advance ship notice (ASN) and the goods are in transit.

In Receiving

The goods have arrived and are in the receiving process (received but not yet delivered or put away).

Delivered

Goods have been delivered to the destination (requester or inventory).

Billed

The supplier invoice has been matched or paid against it.

 

Details

Details

Article ID: 10808
Created
Fri 11/13/26 9:00 PM
Modified
Sat 11/14/26 2:00 PM

Attachments

docx

Amend a Purchase Requisition.docx  · 3 MB Computer

Fri 11/13/26 9:01 PM
;